Interim Payment Certificates (IPCs): How Contractors Bill for Progress
By Artify Solutions Team
Published
Updated
Contractors are rarely paid in one lump sum. They are paid in stages, against certified progress. Here is how interim payment certificates work, what they usually contain, and how to keep the billing connected to your accounts.
Unlike a shop that sells an item and gets paid at the till, a contractor builds over months or years and is paid along the way. The document that makes this possible is the interim payment certificate, usually shortened to IPC.
Understanding how IPCs work, and how they connect to your accounts, is one of the most practical skills in construction finance.
This is general information, not legal advice. The exact process depends on your contract, so always follow its payment terms.
What an IPC is
An interim payment certificate states how much the contractor is entitled to be paid at a particular point in the project. It is typically issued by the engineer, project manager or employer's representative after the contractor submits a claim for the work done.
"Interim" means that the certificate is one of a series. Each one covers progress up to a date, and the series ends with a final certificate at completion.
The usual flow
- Measure the work. The contractor records the work completed in the period, often against the items in the bill of quantities.
- Submit the claim. The contractor sends a progress claim, with supporting measurements and documents.
- Review and certify. The engineer or employer's representative reviews the claim, may adjust it, and certifies an amount.
- Issue the certificate. The certificate states the amount due.
- Invoice and pay. The contractor raises the invoice, and the client pays within the period set by the contract.
What an IPC commonly shows
The layout varies, but a certificate typically builds up the amount like this:
| Line | Meaning |
|---|---|
| Value of work done to date | The cumulative value of work completed, valued at contract rates |
| Variations | Approved changes added to or taken from the contract |
| Less: previously certified | What earlier certificates already covered |
| Less: retention | An amount held back as security, as the contract allows |
| Less: recovery of advance | Repayment of any advance payment already made |
| Add: tax | For example VAT, where it applies |
| Amount due this certificate | The net figure the client pays |
The names and rules depend on the contract. Always check how your own contract defines each line.
Why IPCs matter for cash
An IPC turns completed work into a claim on the client's cash. A delay at any step delays the money, while costs such as wages, materials and subcontractors keep going out. That is why finance teams watch certificates closely:
- how much work has been done but not yet claimed;
- how much has been claimed but not yet certified;
- how much has been certified but not yet paid.
Each of those is a separate pile of money waiting at a different stage, and each should appear in the cash forecast.
Common problems
- Late submission. A claim submitted a week late is paid a week late.
- Disputed measurements. Without good site records, the certified amount can be lower than the work actually done.
- Unrecorded variations. Work done on an instruction that was never recorded is hard to claim.
- Retention forgotten. Amounts held back need to be tracked until they are released.
- Mismatch with accounting. If the invoice, the certificate and the receipt are not linked, the client's balance is hard to reconcile.
Keeping IPCs connected to your accounts
The practical goal is that each certificate flows into receivables, and each receipt is matched to the invoice it settles. A good system lets you:
- raise the progress invoice as an IPC, so it carries the same reference the client expects;
- tag it to the project, so revenue appears against the right job;
- see what the client owes, and for how long, in an aged receivables report;
- adjust balances with credit notes (which reduce the amount owed) and debit notes (which increase it), each with its supporting document.
CAS, the Construction Accounting System by Artify Solutions, lets invoices be raised either as a Standard Tax Invoice or as an Interim Payment Certificate. It shows, for each client, the total invoiced, the total received and the outstanding balance, with a statement of invoices and receipts by project, and a receivables aging report by bracket.
In Artify Next Gen ERP, progress billing links eligible work or contractual milestones to claims and invoices, subject to the applicable contract and approval requirements.
A short checklist
- Agree the claim and certification dates with the client at the start of the project.
- Keep measurement records and supporting documents with each claim.
- Record every variation, with its approval status, before claiming it.
- Track retention and advance recoveries as separate balances.
- Review certified-but-unpaid amounts every week.
- Reconcile each client's balance against invoices and receipts at month end.
Frequently asked questions
Is an IPC the same as an invoice?
No. The certificate states the amount the contractor is entitled to. The invoice is the contractor's request for payment of that amount. In some systems the invoice is raised in the form of an IPC.
Who issues the IPC?
Usually the engineer, project manager or employer's representative named in the contract. The contractor prepares the claim.
What is retention?
An amount withheld from each payment as security and released later under the terms of the contract.
Why can an IPC be lower than the claim?
The reviewer may measure the work differently, reject items or apply deductions. Good records help to support the claim.