Variations and Claims: Recording Scope Changes So They Can Be Paid
By Artify Solutions Team
Published
Updated
Contractors often do extra work on an instruction that is never recorded properly, then struggle to be paid for it. Recording variations and claims at the time, with their evidence, protects both profit and relationships.
This is general information, not legal advice. Notice periods, valuation rules and entitlements depend on your contract, so always follow its terms and take advice on disputes.
A project rarely finishes exactly as it started. The client asks for an extra room. The engineer changes a specification. Ground conditions differ from the drawings. Each change affects cost, time and sometimes the contract value, and each one is a chance to lose money if it is not handled in the right way at the right time.
This article explains the basics of variations and claims and how to keep them connected to your project and finance records.
Variations and claims: two related ideas
- A variation is a change to the agreed scope of work, such as added, omitted or modified work, usually instructed under the contract.
- A claim is a request for additional payment or additional time, for example because of a change, a delay or unforeseen conditions.
The two are often connected. A variation can lead to a claim for the cost of the extra work and any extra time it needs.
Why variations get lost
- Verbal instructions. Work starts on a conversation on site, and nothing is written down.
- Late recording. The change is documented weeks later, when memories and costs have blurred.
- No link to cost. Extra labour, material and equipment are recorded against the project, but not against the change that caused them.
- Missed notice requirements. Many contracts require written notice within a set time. Check your own contract for what applies.
- Weak evidence. Without instructions, measurements, photos and records, the amount is harder to agree.
A practical lifecycle
| Step | What to do | Why it matters |
|---|---|---|
| Instruction | Obtain the instruction in writing, or confirm a verbal one in writing | Shows the work was requested |
| Record | Create a variation record with a reference, date and description | Gives the change an identity |
| Price | Value the work using the contract's rules, with supporting measurements | Gives a basis for agreement |
| Approve | Record who approved it, on what date and for what amount | Shows the change is accepted |
| Update | Reflect the change in contract value, budget and forecast | Keeps reports accurate |
| Bill | Include approved variations in the next progress claim | Turns the change into revenue |
| Track | Follow unapproved variations and claims until they are settled | Prevents silent write-offs |
Keep the evidence together
For each variation or claim, keep the instruction, correspondence, measurements, photographs, daily records, cost records and approvals in one place. When several people work on the same records, a clear version history and a record of who approved what save a great deal of argument later.
Variations and your numbers
A variation changes more than one figure. It can affect:
- the contract value, and so what you can bill;
- the project budget, and so what you can spend;
- the timeline;
- the project's profitability.
If a variation is not recorded, its cost still appears in the project, but its income does not, so the project looks less profitable than it is. This is one reason project margin figures can mislead.
How it works in Artify Next Gen ERP
Artify Next Gen ERP includes Construction and Contracts functionality covering contract lifecycle management, FIDIC contract management, bill of quantities and budgeting, site and work management, progress billing, bonds and guarantees, variations and claims, and contract closeout.
Variation and claim management gives scope changes, and their supporting information, a structured home. The effect of a change on contract value, budget and forecasts can then be reviewed in context. Progress billing links eligible work or contractual milestones to claims and invoices, subject to the applicable contract and approval requirements. Document management adds registered documents with numbers and categories, version history, check-out and check-in locks, and control status, so the evidence for a variation stays with the record.
How these are configured depends on your contracts and approval structure, so confirm the setup you need during planning.
A short checklist
- Get every instruction in writing, or confirm it in writing straight away.
- Record each variation with a reference, date and description.
- Check the contract for notice requirements and follow them.
- Keep measurements, photographs and correspondence with the record.
- Record who approved the variation, when and for how much.
- Update contract value, budget and forecast when a variation is approved.
- Include approved variations in the next progress claim.
- Review unapproved variations and open claims every month.
Frequently asked questions
What if the client will not sign a variation?
Record it anyway, with the evidence, and follow the contract's process for disputed items. Take advice if the amount is significant.
Should I do the work before the variation is approved?
That depends on the contract and the risk. Understand what your contract requires before starting, and record the instruction.
Is a claim the same as a variation?
No. A variation is a change to the scope. A claim is a request for more money or time, which may arise from a variation or from other events.
How often should variations be reviewed?
At least monthly, together with progress claims and project margins.
See it in context
To see contracts, variations and progress billing connected to your project costs, visit erp.artifysols.com to explore the Artify Next Gen ERP demonstration environment, or artifysols.com to speak with the Artify Solutions team. The demonstration uses sample data, and its figures are not verified customer results.